In a scheduling scenario, if task A takes longer than task B, which of the follo

Practice Questions

Q1
In a scheduling scenario, if task A takes longer than task B, which of the following can be inferred?
  1. A must start before B.
  2. B must start before A.
  3. A cannot start until B is finished.
  4. B can be completed while A is ongoing.

Questions & Step-by-Step Solutions

In a scheduling scenario, if task A takes longer than task B, which of the following can be inferred?
  • Step 1: Understand that task A takes more time than task B.
  • Step 2: Recognize that while task A is still being worked on, task B can be finished.
  • Step 3: Conclude that it is possible for task B to be completed before task A is done.