Question: In a scheduling scenario, if task X must be completed before task Y, and task Y must be completed before task Z, which of the following sequences is valid?
Options:
Correct Answer: X, Y, Z
Solution:
The sequence X, Y, Z respects the order that X is before Y and Y is before Z.