Question: If 5 workers can complete a task in 10 days, how many days will 10 workers take to complete the same task? (2023)
Options:
Correct Answer: 5 days
Exam Year: 2023
Solution:
If 5 workers take 10 days, 10 workers will take 10/2 = 5 days.