Question: In a scheduling set, if task J can only start after task K is completed, which of the following is a valid conclusion?

Options:

  1. K can start after J
  2. J can start at any time
  3. K must be completed before J
  4. J is independent of K

Correct Answer: K must be completed before J

Solution:

Task J can only start after K is completed, making this conclusion valid.

In a scheduling set, if task J can only start after task K is completed, which o

Practice Questions

Q1
In a scheduling set, if task J can only start after task K is completed, which of the following is a valid conclusion?
  1. K can start after J
  2. J can start at any time
  3. K must be completed before J
  4. J is independent of K

Questions & Step-by-Step Solutions

In a scheduling set, if task J can only start after task K is completed, which of the following is a valid conclusion?
  • Step 1: Identify the tasks involved. We have task J and task K.
  • Step 2: Understand the relationship between the tasks. Task J can only start after task K is completed.
  • Step 3: Recognize what this means. It means that task K must finish before task J can begin.
  • Step 4: Conclude that since task J depends on task K, it is valid to say that task J cannot start until task K is done.
  • Task Dependency – Understanding that one task must be completed before another can begin.