In a scheduling scenario, if task F is dependent on tasks G and H, which of the

Practice Questions

Q1
In a scheduling scenario, if task F is dependent on tasks G and H, which of the following is a correct statement?
  1. F can start before G and H
  2. G and H must be completed before F
  3. F can be completed at any time
  4. H is independent of F

Questions & Step-by-Step Solutions

In a scheduling scenario, if task F is dependent on tasks G and H, which of the following is a correct statement?
  • Step 1: Understand that task F cannot start until certain other tasks are finished.
  • Step 2: Identify the tasks that task F depends on, which are tasks G and H.
  • Step 3: Realize that for task F to begin, both task G and task H must be completed first.
  • Step 4: Conclude that the correct statement is that task F can only start after both G and H are completed.
No concepts available.
Soulshift Feedback ×

On a scale of 0–10, how likely are you to recommend The Soulshift Academy?

Not likely Very likely