In a scheduling scenario, if G can only start after H and I, what can be inferred? (2023)

Practice Questions

1 question
Q1
In a scheduling scenario, if G can only start after H and I, what can be inferred? (2023)
  1. G is first
  2. H is last
  3. I is last
  4. G is last

Questions & Step-by-step Solutions

1 item
Q
Q: In a scheduling scenario, if G can only start after H and I, what can be inferred? (2023)
Solution: G is last because it can only start after both H and I.
Steps: 4