In a scheduling problem, if event P is scheduled for 10 AM and event Q cannot start before 11 AM, which of the following statements is true?

Practice Questions

1 question
Q1
In a scheduling problem, if event P is scheduled for 10 AM and event Q cannot start before 11 AM, which of the following statements is true?
  1. P and Q can occur simultaneously.
  2. Q can start at 10:30 AM.
  3. P must end before Q starts.
  4. P can start after Q.

Questions & Step-by-step Solutions

1 item
Q
Q: In a scheduling problem, if event P is scheduled for 10 AM and event Q cannot start before 11 AM, which of the following statements is true?
Solution: P must end before Q starts since Q cannot start before 11 AM.