In a scheduling problem, if event P is scheduled for 10 AM and event Q cannot st

Practice Questions

Q1
In a scheduling problem, if event P is scheduled for 10 AM and event Q cannot start before 11 AM, which of the following statements is true?
  1. P and Q can occur simultaneously.
  2. Q can start at 10:30 AM.
  3. P must end before Q starts.
  4. P can start after Q.

Questions & Step-by-Step Solutions

In a scheduling problem, if event P is scheduled for 10 AM and event Q cannot start before 11 AM, which of the following statements is true?
  • Step 1: Identify the time for event P, which is scheduled for 10 AM.
  • Step 2: Identify the time constraint for event Q, which cannot start before 11 AM.
  • Step 3: Understand that for event Q to start at 11 AM, event P must finish before that time.
  • Step 4: Conclude that since event P is at 10 AM and event Q cannot start until 11 AM, event P must end before event Q starts.