Q1
In a scheduling set, if task E can only start after both tasks A and D are completed, which of the following is a possible order?
  1. A, D, E, B, C
  2. D, A, B, C, E
  3. E, A, D, B, C
  4. B, C, A, D, E

Questions & Step-by-Step Solutions

In a scheduling set, if task E can only start after both tasks A and D are completed, which of the following is a possible order?
  • Step 1: Identify the tasks involved: A, D, and E.
  • Step 2: Understand the condition: Task E can only start after both tasks A and D are completed.
  • Step 3: Look at the proposed order: A, D, E, B, C.
  • Step 4: Check if A is completed before E starts: Yes, A is first in the order.
  • Step 5: Check if D is completed before E starts: Yes, D is second in the order.
  • Step 6: Since both A and D are completed before E starts, the order is valid.