In a scheduling set, if task E can only start after both tasks A and D are completed, which of the following is a possible order?

Practice Questions

1 question
Q1
In a scheduling set, if task E can only start after both tasks A and D are completed, which of the following is a possible order?
  1. A, D, E, B, C
  2. D, A, B, C, E
  3. E, A, D, B, C
  4. B, C, A, D, E

Questions & Step-by-step Solutions

1 item
Q
Q: In a scheduling set, if task E can only start after both tasks A and D are completed, which of the following is a possible order?
Solution: The order A, D, E, B, C is valid as E starts after A and D.
Steps: 6