Question: If the budgeted cost for direct materials is $50,000 and the actual cost is $55,000, what is the direct materials price variance?

Options:

  1. $5,000 Favorable
  2. $5,000 Unfavorable
  3. $10,000 Favorable
  4. $10,000 Unfavorable

Correct Answer: $5,000 Unfavorable

Solution:

Direct materials price variance = Actual Cost - Budgeted Cost = $55,000 - $50,000 = $5,000 Unfavorable.

If the budgeted cost for direct materials is $50,000 and the actual cost is $55,

Practice Questions

Q1
If the budgeted cost for direct materials is $50,000 and the actual cost is $55,000, what is the direct materials price variance?
  1. $5,000 Favorable
  2. $5,000 Unfavorable
  3. $10,000 Favorable
  4. $10,000 Unfavorable

Questions & Step-by-Step Solutions

If the budgeted cost for direct materials is $50,000 and the actual cost is $55,000, what is the direct materials price variance?
  • Step 1: Identify the budgeted cost for direct materials, which is $50,000.
  • Step 2: Identify the actual cost for direct materials, which is $55,000.
  • Step 3: Calculate the direct materials price variance by subtracting the budgeted cost from the actual cost.
  • Step 4: Perform the calculation: $55,000 (actual cost) - $50,000 (budgeted cost) = $5,000.
  • Step 5: Determine if the variance is favorable or unfavorable. Since the actual cost is higher than the budgeted cost, the variance is unfavorable.
  • Direct Materials Price Variance – The difference between the actual cost of direct materials and the budgeted cost, indicating whether the cost was higher or lower than expected.