Question: If a company has a budgeted cost of $100,000 and an actual cost of $90,000, what is the cost variance?
Options:
Correct Answer: $10,000 Favorable
Solution:
Cost Variance = Actual Cost - Budgeted Cost = $90,000 - $100,000 = $10,000 Favorable.