If a company has a budgeted cost of $100,000 and an actual cost of $90,000, what is the cost variance?

Practice Questions

1 question
Q1
If a company has a budgeted cost of $100,000 and an actual cost of $90,000, what is the cost variance?
  1. $10,000 Favorable
  2. $10,000 Unfavorable
  3. $90,000 Favorable
  4. $90,000 Unfavorable

Questions & Step-by-step Solutions

1 item
Q
Q: If a company has a budgeted cost of $100,000 and an actual cost of $90,000, what is the cost variance?
Solution: Cost Variance = Actual Cost - Budgeted Cost = $90,000 - $100,000 = $10,000 Favorable.
Steps: 6