Question: A company budgeted $200,000 for production costs but incurred $220,000. What is the variance?
Options:
Correct Answer: $20,000 Unfavorable
Solution:
Variance = Actual Costs - Budgeted Costs = $220,000 - $200,000 = $20,000 Unfavorable.