Question: If the budgeted overhead is $200,000 and the actual overhead is $220,000, what is the overhead variance?
Options:
Correct Answer: $20,000 Unfavorable
Solution:
Overhead variance = Actual Overhead - Budgeted Overhead = $220,000 - $200,000 = $20,000 Unfavorable.