Question: In a project management scenario, if a task is estimated to take 15 hours and the team has 3 members, how many hours will each member need to work if they share the workload equally?

Options:

  1. 3 hours
  2. 5 hours
  3. 10 hours
  4. 15 hours

Correct Answer: 5 hours

Solution:

If the task takes 15 hours and is shared equally among 3 members, each member will work 15 hours / 3 = 5 hours.

In a project management scenario, if a task is estimated to take 15 hours and th

Practice Questions

Q1
In a project management scenario, if a task is estimated to take 15 hours and the team has 3 members, how many hours will each member need to work if they share the workload equally?
  1. 3 hours
  2. 5 hours
  3. 10 hours
  4. 15 hours

Questions & Step-by-Step Solutions

In a project management scenario, if a task is estimated to take 15 hours and the team has 3 members, how many hours will each member need to work if they share the workload equally?
  • Step 1: Identify the total time needed for the task, which is 15 hours.
  • Step 2: Identify the number of team members available to work on the task, which is 3 members.
  • Step 3: To find out how many hours each member needs to work, divide the total time (15 hours) by the number of members (3).
  • Step 4: Perform the calculation: 15 hours ÷ 3 members = 5 hours per member.
  • Step 5: Conclude that each member will need to work 5 hours.
  • Workload Distribution – Understanding how to divide total task hours among team members.
  • Basic Division – Applying division to calculate individual contributions from a total.