Scheduling Sets

Download Q&A
Q. In a project with tasks P, Q, R, S, and T, if P must precede Q and R must follow S, which of the following is a possible order?
  • A. P, Q, S, R, T
  • B. S, R, P, Q, T
  • C. Q, P, S, R, T
  • D. R, S, P, Q, T
Q. In a scheduling problem, if event P is scheduled for 10 AM and event Q cannot start before 11 AM, which of the following statements is true?
  • A. P and Q can occur simultaneously.
  • B. Q can start at 10:30 AM.
  • C. P must end before Q starts.
  • D. P can start after Q.
Q. In a scheduling scenario, if event A is scheduled for 2 PM and event B for 4 PM, which of the following statements is correct?
  • A. Event A can be rescheduled to 3 PM.
  • B. Event B can start at 3:30 PM.
  • C. Event A must end before event B starts.
  • D. Event B can start at 2:30 PM.
Q. In a scheduling scenario, if task A must be completed before task B and task C can be done at any time, which of the following is a possible order?
  • A. C, A, B
  • B. B, A, C
  • C. A, C, B
  • D. A, B, C
Q. In a scheduling scenario, if task A takes 2 hours, task B takes 3 hours, and task C takes 1 hour, which of the following combinations allows for the earliest completion of all tasks if A must be done before B?
  • A. A, B, C
  • B. C, A, B
  • C. B, A, C
  • D. A, C, B
Q. In a scheduling scenario, if task A takes 2 hours, task B takes 3 hours, and task C takes 1 hour, which of the following combinations can be completed in 5 hours?
  • A. A and B
  • B. B and C
  • C. A and C
  • D. A, B, and C
Q. In a scheduling scenario, if task A takes longer than task B, which of the following can be inferred?
  • A. A must start before B.
  • B. B must start before A.
  • C. A cannot start until B is finished.
  • D. B can be completed while A is ongoing.
Q. In a scheduling scenario, if task B cannot start until task A is finished, and task C cannot start until task B is finished, which of the following is a valid conclusion?
  • A. A must finish before C
  • B. B can start before A
  • C. C can start before B
  • D. A can start after C
Q. In a scheduling scenario, if task B is dependent on both tasks A and C being completed, which of the following sequences is valid?
  • A. C, A, B, D
  • B. A, B, C, D
  • C. B, A, C, D
  • D. A, C, D, B
Q. In a scheduling scenario, if task E can only start after task D is completed, which of the following is a valid implication?
  • A. D can start after E
  • B. E can start before D
  • C. D must be completed before E
  • D. E and D can start simultaneously
Q. In a scheduling scenario, if task F is dependent on tasks G and H, which of the following is a correct statement?
  • A. F can start before G and H
  • B. G and H must be completed before F
  • C. F can be completed at any time
  • D. H is independent of F
Q. In a scheduling scenario, if task F must be completed before task G and task H can be done at any time, which of the following is true?
  • A. H must be done before F.
  • B. G can start before F.
  • C. F must be done before H.
  • D. G cannot start until F is done.
Q. In a scheduling scenario, if task J must be completed before task K, and task L can be done at any time, which of the following is true?
  • A. K can start before J.
  • B. L must be completed before J.
  • C. J must be completed before K, but L can be done anytime.
  • D. K must be completed before L.
Q. In a scheduling scenario, if task X must be completed before task Y, and task Y must be completed before task Z, which of the following is a valid inference?
  • A. X can start after Y
  • B. Z can start before Y
  • C. Y can start after X
  • D. Z must start after X
Q. In a scheduling scenario, if task X must be completed before task Y, and task Y must be completed before task Z, which of the following sequences is valid?
  • A. Z, Y, X
  • B. X, Y, Z
  • C. Y, Z, X
  • D. Z, X, Y
Q. In a scheduling set involving five friends, A, B, C, D, and E, if A cannot sit next to B, and C must sit between D and E, which of the following arrangements is valid?
  • A. A, C, D, E, B
  • B. B, A, C, E, D
  • C. D, C, E, A, B
  • D. C, D, A, B, E
Q. In a scheduling set involving five tasks A, B, C, D, and E, if task A must be completed before task B, and task C must be completed before task D, which of the following is a valid sequence?
  • A. A, B, C, D, E
  • B. C, D, A, B, E
  • C. B, A, D, C, E
  • D. E, A, C, D, B
Q. In a scheduling set involving four tasks A, B, C, and D, if task A must be completed before task B, and task C cannot start until task D is finished, which of the following sequences is valid?
  • A. A, B, C, D
  • B. D, C, A, B
  • C. B, A, D, C
  • D. C, D, A, B
Q. In a scheduling set, if task E can only start after both tasks A and D are completed, which of the following is a possible order?
  • A. A, D, E, B, C
  • B. D, A, B, C, E
  • C. E, A, D, B, C
  • D. B, C, A, D, E
Q. In a scheduling set, if task E can only start after task D and task D can only start after task C, which of the following is a valid order?
  • A. C, D, E, A
  • B. D, C, E, A
  • C. E, D, C, A
  • D. A, C, D, E
Q. In a scheduling set, if task E must be completed before task D, and task D must be completed before task C, which of the following sequences is valid?
  • A. C, D, E
  • B. E, D, C
  • C. D, C, E
  • D. E, C, D
Q. In a scheduling set, if task G must be completed before task H, and task H must be completed before task I, which of the following sequences is invalid?
  • A. G, H, I
  • B. H, G, I
  • C. G, I, H
  • D. I, H, G
Q. In a scheduling set, if task J can only start after task K is completed, which of the following is a valid conclusion?
  • A. K can start after J
  • B. J can start at any time
  • C. K must be completed before J
  • D. J is independent of K
Q. In a set of tasks A, B, C, D, and E, if A must be done before B and C, and C must be done before D, which of the following is a possible order?
  • A. B, A, C, D, E
  • B. A, C, B, D, E
  • C. C, A, B, D, E
  • D. A, B, D, C, E
Q. In a set of tasks where A must be completed before B, and C must be completed before A, which of the following sequences is valid?
  • A. C, A, B
  • B. A, C, B
  • C. B, A, C
  • D. C, B, A
Q. In a set of tasks where A must be completed before C, and C must be completed before D, which of the following sequences is invalid?
  • A. A, C, D
  • B. C, A, D
  • C. A, D, C
  • D. D, C, A
Q. In a set of tasks where A must be completed before D, and D must be completed before E, which of the following is a valid order?
  • A. E, D, A
  • B. A, D, E
  • C. D, A, E
  • D. A, E, D
Q. In a set of tasks where A must precede B and C must follow B, which of the following is a correct order?
  • A. B, A, C
  • B. A, C, B
  • C. A, B, C
  • D. C, B, A
Q. In a set of tasks where task J must be completed before task K and task L can be done at any time, which of the following is a valid sequence?
  • A. K, J, L
  • B. J, K, L
  • C. L, J, K
  • D. J, L, K
Q. In a set of tasks where task J must precede task K and task L can occur at any time, which of the following sequences is valid?
  • A. K, J, L
  • B. J, L, K
  • C. L, K, J
  • D. J, K, L