Scheduling Sets

Download Q&A
Q. If task M can only start after task N and task O, which of the following is a correct implication?
  • A. M can start before N.
  • B. M can start before O.
  • C. M can start only after both N and O.
  • D. M can start at the same time as N.
Q. If task M must be completed before task N, and task N must be completed before task O, which of the following is a valid sequence?
  • A. O, N, M
  • B. M, N, O
  • C. N, O, M
  • D. O, M, N
Q. If task M must be completed before task N, and task N must be completed before task O, which of the following is a valid inference?
  • A. M can start after N
  • B. O can start before M
  • C. N can start before M
  • D. M must be completed before O
Q. If task Q must be completed before task R and task S can be done at any time, which of the following is a valid sequence?
  • A. R, Q, S
  • B. Q, S, R
  • C. S, R, Q
  • D. Q, R, S
Q. If task T must be completed before task U, and task V can start at any time, which of the following is true?
  • A. U can start before T.
  • B. V must be completed before T.
  • C. T must be completed before U, but V can start anytime.
  • D. U must be completed before V.
Q. If task X is dependent on tasks Y and Z being completed first, which of the following statements is true?
  • A. X can start before Y and Z
  • B. Y and Z can start after X
  • C. X can only start after Y and Z
  • D. Y and Z are independent of X
Q. If tasks A, B, and C are interdependent such that A must be completed before B, and B must be completed before C, which of the following is a valid order?
  • A. C, B, A
  • B. B, A, C
  • C. A, B, C
  • D. A, C, B
Q. If tasks A, B, and C are interdependent such that A must precede B, and B must precede C, which of the following sequences is valid?
  • A. C, B, A
  • B. A, C, B
  • C. A, B, C
  • D. B, A, C
Q. If tasks A, B, and C are scheduled such that A must be completed before B, and B must be completed before C, which of the following sequences is valid?
  • A. C, B, A
  • B. A, C, B
  • C. A, B, C
  • D. B, A, C
Q. If tasks A, B, and C are to be completed in that order, but task C can be delayed until after task D is completed, which of the following is a valid completion order?
  • A. A, B, D, C
  • B. D, A, B, C
  • C. B, A, C, D
  • D. C, D, A, B
Q. If tasks A, B, and C are to be scheduled such that A must precede B, and B must precede C, which of the following sequences is valid?
  • A. C, B, A
  • B. A, C, B
  • C. A, B, C
  • D. B, A, C
Q. If tasks A, B, and C must be completed before task D, which of the following is an invalid sequence?
  • A. A, B, C, D
  • B. B, C, A, D
  • C. C, A, D, B
  • D. A, C, B, D
Q. If tasks A, B, and C must be completed in that order, which of the following is an invalid sequence?
  • A. A, B, C
  • B. B, A, C
  • C. A, C, B
  • D. C, A, B
Q. If tasks A, B, and C must be completed in that order, which of the following sequences is valid?
  • A. C, B, A
  • B. A, C, B
  • C. B, A, C
  • D. A, B, C
Q. If tasks A, B, and C must be completed in that order, which of the following sequences is invalid?
  • A. A, B, C
  • B. B, A, C
  • C. A, C, B
  • D. C, A, B
Q. If tasks L, M, and N are to be completed with L before M and N, which of the following sequences is correct?
  • A. M, L, N
  • B. L, N, M
  • C. N, M, L
  • D. L, M, N
Q. If tasks M, N, O, and P are scheduled such that M must be done before N and O, and N must be done before P, which of the following sequences is valid?
  • A. M, N, O, P
  • B. N, M, O, P
  • C. O, M, N, P
  • D. P, N, M, O
Q. If tasks P, Q, R, and S are scheduled such that P must be completed before Q, and R must be completed before S, which of the following is a possible order?
  • A. P, Q, R, S
  • B. R, S, P, Q
  • C. Q, P, S, R
  • D. S, R, Q, P
Q. If the meetings of a project team are scheduled on Monday, Wednesday, and Friday, and no two meetings can occur on consecutive days, which day can be added for an additional meeting without violating the schedule?
  • A. Tuesday
  • B. Thursday
  • C. Saturday
  • D. Sunday
Q. In a project involving tasks A, B, C, and D, if A and B can be done simultaneously but must be completed before C, and D can be done at any time, which of the following is a correct sequence?
  • A. A, B, C, D
  • B. C, A, B, D
  • C. D, A, B, C
  • D. B, A, C, D
Q. In a project involving tasks A, B, C, and D, if task D can only start after task B is completed, which of the following is a possible order of tasks?
  • A. A, D, B, C
  • B. B, A, C, D
  • C. C, B, A, D
  • D. D, A, B, C
Q. In a project involving tasks A, B, C, and D, if task D can only start after task B is completed, which of the following is a valid conclusion?
  • A. B must be completed before D
  • B. D can start before B
  • C. A can start after D
  • D. C must be completed before B
Q. In a project involving tasks A, B, C, and D, if task D cannot be started until task B is completed, which of the following is a valid implication?
  • A. B must be completed before D.
  • B. D can start before B.
  • C. A can start before B and D.
  • D. C must be completed before D.
Q. In a project involving tasks A, B, C, and D, if task D cannot start until task B is completed, which of the following is a valid inference?
  • A. B must be completed before D.
  • B. D can start before B.
  • C. A can start before B.
  • D. C must be completed before D.
Q. In a project involving tasks A, B, C, and D, if task D is dependent on both A and B, which of the following is a valid completion order?
  • A. B, A, D, C
  • B. A, C, B, D
  • C. C, A, B, D
  • D. A, B, D, C
Q. In a project involving tasks X, Y, Z, and W, if W cannot start until Y is completed, and Z can only start after W, which of the following is a valid sequence?
  • A. Y, W, Z, X
  • B. W, Y, Z, X
  • C. Z, W, Y, X
  • D. X, Y, W, Z
Q. In a project timeline, if Task 1 must be completed before Task 2, and Task 3 can start only after Task 2, which of the following sequences is valid?
  • A. Task 1, Task 3, Task 2
  • B. Task 2, Task 1, Task 3
  • C. Task 1, Task 2, Task 3
  • D. Task 3, Task 1, Task 2
Q. In a project with tasks A, B, C, and D, if task C can only start after both A and B are completed, which of the following is a valid sequence?
  • A. A, B, C, D
  • B. B, A, D, C
  • C. C, A, B, D
  • D. D, C, A, B
Q. In a project with tasks P, Q, R, and S, if P must be completed before Q and R, and S can be done at any time, which of the following is a possible order of completion?
  • A. P, Q, R, S
  • B. R, P, Q, S
  • C. S, P, Q, R
  • D. Q, R, P, S
Q. In a project with tasks P, Q, R, S, and T, if P must be completed before Q and R, and R must be completed before S, which of the following is a valid conclusion?
  • A. S can start before P.
  • B. Q can start after R.
  • C. R can start after P.
  • D. T must be completed before P.